901 Valencia - Commercial · Status:
Contract Value
$0.00
Budgeted Cost
$0.00
Actual Cost
$55,966.07
$0.00 pending verification · of $0.00 budgeted
Realized Profit
($55,966.07)
expected $6,112.62 · variance ($62,078.69)
Budget-overrun & variance flags(at-risk = actual ≥ 90% of scope budget)
Projected cost ($55,966.07) exceeds the estimated cost ($0.00) — profit target will not be met. Variance ($62,078.69) vs expected profit.
- At riskMobilization and Rental Equipment
Cost by category
Billing progress
Exceptions (13)
- Source NeededCity and County of San Francisco - 04/17/26 — City and County of San Francisco ($516.00) needs a scope mappingMap
- Source NeededSAN FRANCISCO PERMIT - 05/29/26 — San Francisco Permit ($654.92) needs a scope mappingMap
- Source NeededSF SERVICE FEE - 05/29/26 — San Francisco ($14.74) needs a scope mappingMap
- Source NeededAmazon - 06/16/26 — Amazon ($217.07) needs a scope mappingMap
- Source NeededAmazon - 06/16/26 — Amazon ($114.05) needs a scope mappingMap
- Source NeededSubcon Fredy - 06/24/26 — Subcontractor / Fredy ($5,000.00) needs a scope mappingMap
- Source NeededSubcon Fredy - 07/10/26 (part 1) — Subcontractor / Fredy ($7,000.00) needs a scope mappingMap
- Source NeededSubcon Fredy - 07/10/26 (part 2) — Subcontractor / Fredy ($8,000.00) needs a scope mappingMap
- Source NeededSubcon Fredy - 07/17/26 — Subcontractor / Fredy ($5,000.00) needs a scope mappingMap
- Source NeededSubcon Fredy - 07/21/26 — Subcontractor / Fredy ($10,000.00) needs a scope mappingMap
- Source NeededSubcon Fredy - 07/24/26 — Subcontractor / Fredy ($15,000.00) needs a scope mappingMap
- Source NeededDBS - 08/19/26 — Discount Builders Supply ($174.65) needs a scope mappingMap
- Missing invoiceFinal 10% / Closeout: Final 10% invoice not found. Need to verify.
12 ledger row(s) totalling $51,691.43 are unassigned to a scope.