Project Cost Ledger

901 Valencia - Commercial

DateRef #Vendor / PayeeDescriptionScope AssignmentCost CategoryDebit / CostCreditNet CostRunning Actual CostEvidence StatusSource / Reconciliation Note
2026-04-1712335City and County of San FranciscoCity and County of San Francisco - 04/17/26UNASSIGNED / NEEDS SCOPE MAPPINGPermit / Fee$516.00$0.00$516.00$516.00Found in invoice 12335Listed under invoice 12335 in Invoice Breakdown.
2026-05-2912335San Francisco PermitSAN FRANCISCO PERMIT - 05/29/26UNASSIGNED / NEEDS SCOPE MAPPINGPermit / Fee$654.92$0.00$654.92$1,170.92Found in invoice 12335Listed under invoice 12335 in Invoice Breakdown.
2026-05-2912335San FranciscoSF SERVICE FEE - 05/29/26UNASSIGNED / NEEDS SCOPE MAPPINGPermit / Fee$14.74$0.00$14.74$1,185.66Found in invoice 12335Listed under invoice 12335 in Invoice Breakdown.
2026-06-1112335United RentalsUnited Rentals - 06/11/26Mobilization and Rental EquipmentEquipment Rental$2,010.27$0.00$2,010.27$3,195.93Found in invoice 12335Listed under invoice 12335 in Invoice Breakdown.
2026-06-1612335AmazonAmazon - 06/16/26UNASSIGNED / NEEDS SCOPE MAPPINGMaterials$217.07$0.00$217.07$3,413.00Found in invoice 12335; source neededListed under invoice 12335; underlying receipt/order should be retained for support.
2026-06-1612335AmazonAmazon - 06/16/26UNASSIGNED / NEEDS SCOPE MAPPINGMaterials$114.05$0.00$114.05$3,527.05Found in invoice 12335; source neededListed under invoice 12335; underlying receipt/order should be retained for support.
2026-06-2412488Subcontractor / FredySubcon Fredy - 06/24/26UNASSIGNED / NEEDS SCOPE MAPPINGLabor$5,000.00$0.00$5,000.00$8,527.05Found in invoice 12488; bank transfer confirmedMatches confirmed 06/24/2026 subcontractor bank transfer for $5,000.
2026-07-1012457Subcontractor / FredySubcon Fredy - 07/10/26 (part 1)UNASSIGNED / NEEDS SCOPE MAPPINGLabor$7,000.00$0.00$7,000.00$15,527.05Found in invoice 12457; bank transfer confirmedPart of the $15,000 labor cost listed under invoice 12457; confirmed bank transfer $7,000.
2026-07-1012457Subcontractor / FredySubcon Fredy - 07/10/26 (part 2)UNASSIGNED / NEEDS SCOPE MAPPINGLabor$8,000.00$0.00$8,000.00$23,527.05Found in invoice 12457; bank transfer confirmedPart of the $15,000 labor cost listed under invoice 12457; confirmed bank transfer $8,000.
2026-07-1412488United RentalsUnited Rentals - 07/14/26Mobilization and Rental EquipmentEquipment Rental$377.40$0.00$377.40$23,904.45Found in invoice 12488Listed under invoice 12488 in Invoice Breakdown.
2026-07-1512488United RentalsUnited Rentals - 07/15/26Mobilization and Rental EquipmentEquipment Rental$377.40$0.00$377.40$24,281.85Found in invoice 12488Listed under invoice 12488 in Invoice Breakdown.
2026-07-1712488Subcontractor / FredySubcon Fredy - 07/17/26UNASSIGNED / NEEDS SCOPE MAPPINGLabor$5,000.00$0.00$5,000.00$29,281.85Found in invoice 12488; bank transfer confirmedMatches confirmed 07/17/2026 subcontractor bank transfer for $5,000.
2026-07-2112488Subcontractor / FredySubcon Fredy - 07/21/26UNASSIGNED / NEEDS SCOPE MAPPINGLabor$10,000.00$0.00$10,000.00$39,281.85Found in invoice 12488; bank transfer confirmedMatches confirmed 07/21/2026 subcontractor bank transfer for $10,000.
2026-07-2212488United RentalsUnited Rentals - 07/22/26Mobilization and Rental EquipmentEquipment Rental$754.77$0.00$754.77$40,036.62Found in invoice 12488Listed under invoice 12488 in Invoice Breakdown.
2026-07-2412335Subcontractor / FredySubcon Fredy - 07/24/26UNASSIGNED / NEEDS SCOPE MAPPINGLabor$15,000.00$0.00$15,000.00$55,036.62Found in invoice 12335; bank transfer confirmedMatches confirmed 07/24/2026 subcontractor bank transfer for $15,000. Possible overlap with invoice 12457 $15,000 labor line - verify.
2026-08-1212488United RentalsUnited Rentals - 08/12/26Mobilization and Rental EquipmentEquipment Rental$754.80$0.00$754.80$55,791.42Found in invoice 12488Listed under invoice 12488 in Invoice Breakdown.
2026-08-1912488Discount Builders SupplyDBS - 08/19/26UNASSIGNED / NEEDS SCOPE MAPPINGMaterials$174.65$0.00$174.65$55,966.07Found in invoice 12488Listed under invoice 12488 in Invoice Breakdown.
Total (17 rows)$55,966.07$0.00$55,966.07$55,966.07

Net Cost = Debit − Credit. Running Actual Cost = cumulative Net Cost in date order. Rows marked "Needs Verification" are excluded from reconciliation totals. Edits to existing rows are made in the linked Google Sheet; new entries can be added here or via Import. Filtered totals show $55,966.07 net.