Estimate-to-Actual Scope Reconciliation

901 Valencia - Commercial

ScopeApproved PriceEstimated Cost BudgetExpected ProfitSupported Actual CostRemaining Budget $Remaining Budget %Reconciliation StatusBudget Risk
Mobilization and Rental EquipmentNoted cost from paid invoices 12335 and 12488: $4,274.64.$4,880.48$4,436.80$443.68$4,274.64$162.163.7%Mapped / under budgetOn track
Leak Detection and Minor Repairs$1,982.82$1,802.56$180.26$0.00$1,802.56100.0%No actual cost mapped yetOn track
Drywall and Insulation$32,598.72$29,635.20$2,963.52$0.00$29,635.20100.0%No actual cost mapped yetOn track
Lighting Infrastructure$12,172.16$11,065.60$1,106.56$0.00$11,065.60100.0%No actual cost mapped yetOn track
Flooring Prep$3,518.90$3,199.00$319.90$0.00$3,199.00100.0%No actual cost mapped yetOn track
Heater Installation$3,220.00$2,299.00$921.00$0.00$2,299.00100.0%No actual cost mapped yetOn track
Door Repair(s) Front and Back$1,954.70$1,777.00$177.70$0.00$1,777.00100.0%No actual cost mapped yetOn track
Plumbing$0.00$0.00$0.00$0.00$0.00No actual cost mapped yetOn track
UNASSIGNED / NEEDS SCOPE MAPPINGCatch-all for unmapped costs. Noted cost from paid invoices 12335, 12457, and 12488: $51,691.43; scope mapping still required.$0.00$0.00$0.00$51,691.43($51,691.43)Needs scope allocationneeds allocation
TOTAL$60,327.78$54,215.16$6,112.62$55,966.07($1,750.91)-3.2%

Supported Actual Cost sums ledger rows assigned to the scope, excluding rows needing verification. At-risk threshold: 54215.16% of scope budget.